Chapter 2 2-49
Library Installation
Moving or Shipping the Library
Library Installation
Library Installation
5. Power off the library. The power standby switch is recessed to avoid
accidental power cycles.
6. Remove all cords, cables, and terminators when shipping the library.
For an internal move, only disconnect the power cables, SCSI cables,
and Fibre Channel connection from the host, hub, or switch.
NOTE You do not need to remove the SCSI cables that connect the controller or
the Fibre Channel interface card to the drive modules, unless the library
is being shipped.
7. To move a stand-alone library, place it on a cart, wheel it to its new
location, and reconnect it using the procedures in Connecting and
Powering on the Library (for Models 2/20, 4/40, and 6/60) on
page 2-28.
For libraries mounted in a rack, proceed to the next step.
For shipping, place the library in the original packing materials or
packaging kit.
8. Extend the racks anti-tip foot.
WARNING Failure to extend the anti-tip foot could result in personal injury
or damage to the library.
9. Open the magazine doors and loosen the screws that lock the library
into place. The screws are located in front of the trim brackets.
10.Remove the stop bracket. (See Figure 2-9 on page 2-17, and
Figure 2-10 on page 2-18.)
11.Push the library out of the rack until it hits the latch stops
(approximately 60% out of the rack).
12.Reattach the lifting straps to the library.