Library Installation
Installing the Library into a Rack (for Model 2/20, 4/40, and 6/60)
Library Installation
Library Installation
Figure 2-5 Clip Nut Placement (Model 6/60)
2. Align the upper rail with the top two clip nuts, and loosely install a
screw into each clip nut. Slide the rail out so that it equals the rack
depth, and attach to the back clip nuts. To allow for enough clearance,
do not tighten these screws until you have installed the library.
NOTE Ensure that you are using the appropriate holes in the upper rail to
allow for enough clearance, illustrated in Figure 2-6. Models 4/40 and
6/60 need additional clearance at the top of the library to accommodate
the vertical lift assembly. The clearance between the top and bottom rails
should be: Model 2/20 = 8.5 inches; Model 4/40 = 17 inches; Model 6/60
= 25.5 inches.