CAUTION:
Use safe practices when lifting.
6. Slide the DS4500 Storage Subsystem out of the rack cabinet and set it on a
level, dry surface.
7. Perform one of the following tasks:
v If you are shipping the DS4500 Storage Subsystem to another location,
replace all CRUs in the DS4500 Storage Subsystem. Carefully pack the unit
in its original shipping container. You are finished with this procedure.
v If you are moving the DS4500 Storage Subsystem to another rack cabinet,
remove the support rails and power cords from the old rack cabinet and
install them in the new one.
8. To install the DS4500 Storage Subsystem into a rack cabinet in the new
location, perform the following steps:
a. Slide the DS4500 Storage Subsystem into the rack cabinet.
b. Insert and tighten two of the screws that you removed in Step 5 on the
inside front of the DS4500 Storage Subsystem.
c. Insert and tighten the remaining two screws that you removed in Step 5 on
the inside rear of the DS4500 Storage Subsystem.
9. Replace all CRUs in the DS4500 Storage Subsystem.
10. Connect the interface cables and host Fibre Channel cables that you labeled in
Step 3 on page 143.
11. Connect the remaining cables to the DS4500 Storage Subsystem.
12. Turn on power to the DS4500 Storage Subsystem. Use the procedure in
“Powering on the storage subsystem” on page 119.
13. Replace the DS4500 Storage Subsystem bezel (see “Replacing the front
bezel” on page 44).
144 IBM TotalStorage DS4500 Fibre Channel Storage Subsystem: Installation, User’s, and Maintenance Guide