– 5 –
LOCATION
The equipment area must be kept free and clear of combustible substances.
This broiler is design certified for installation with the following minimum clearances from combustible
and noncombustible adjacent wall construction:
COMBUSTIBLE NONCOMBUSTIBLE
MODELS CONSTRUCTION CONSTRUCTION
GHCB40 Back 6" (152 mm) 0"
GHCB40C Right Side 6" (152 mm) 0"
GHCB44 Left Side 6" (152 mm) 0"
Floor 6" (152 mm) 0"
COMBUSTIBLE NONCOMBUSTIBLE
MODEL CONSTRUCTION CONSTRUCTION
GHIR44 Back 4" (102 mm) 0"
Right Side 0" 0"
Left Side 0" 0"
Floor 6" (152 mm) 0"
COMBUSTIBLE NONCOMBUSTIBLE
MODEL CONSTRUCTION CONSTRUCTION
HCB2 Back 4" (102 mm) 0"
Right Side 4" (102 mm) 0"
Left Side 4" (102 mm) 0"
Floor 6" (152 mm) 0"
COMBUSTIBLE NONCOMBUSTIBLE
MODEL CONSTRUCTION CONSTRUCTION
IR2 Back 4" (102 mm) 0"
Right Side 0" 0"
Left Side 0" 0"
Floor 6" (152 mm) 0"
The installation location must allow adequate clearances for servicing and proper operation. A
minimum front clearance of 35" (889 mm) is required.
Do not obstruct the flow of combustion and ventilation air. Adequate clearance for air openings into
the combustion chamber must be provided. Make sure there is an adequate supply of air in the room
to replace air taken by ventilating systems and allow for combustion gas at the broiler burners.