BackĆtoĆBack Installation:
Never install a valve body upside
down. If two valves are installed
in a backĆtoĆback configuration,
install both as previously
instructed. The supplies to one of
the valves will be reversed.
To correct the valve control on
the reversed valve, remove the
plaster guard, cap assembly and
collar. Rotate the cap assembly
and collar 180° (tab on bottom),
reassemble and tighten the
screws.
Reinstall the plaster guard.
Cap
Assembly
Cold
Supply
Screws
Hot
Supply
Tab
Valve
Body
180_
Collar
Plaster
Guard
INSTALLATION CHECKOUT
4.
Install caps to the temporary bath
and shower nipples.
Turn on the hot and cold water
supplies and check the new
installation for leaks.
Remove the caps from the
temporary nipples.
Remove the plaster guard.
Turn the valve stem to the On"
position and cycle the control
through its operating range.
Turn the valve off.
If the valve has stops, rotate
both stop adjustments fully
clockwise.
Turn the valve on and verify
that water does not run.
Turn the valve off and rotate
both stop adjustments fully
counterclockwise.
Reinstall the plaster guard.
INSTALL WALL
5.
Thick Wall Installation (Tile,
Plaster, Marble, etc.): Provide
a 5Ć9/16" (141.1cm) diameter hole
in the rough wall material. The
flat front surface of the plaster
guard must be flush with the
finished wall.
Complete the finished wall.
Do not remove the plaster guard
until instructed.
2Ć3/4" (7cm)-4" (10.2cm)
RoughĆIn Depth
Finished W all
Plaster
Guard
UP
HOT
5Ć9/16"
(141.1cm) D.